Taxiway Kilo and RWY 30 Extension
Department
Aviation
Client
Jandakot Airport Holdings
Time
Sep 2018 to Sep 2019
Value
Approx $7m
Team
WCC: Daniel Laudehr, Ryan Martin
Scope of Works
- 26,000m2 of Taxiway Construction
- 17,000m2 of Asphalt Overlay
- 15,000m2 of Runway Extension
- 8,000m2 of Apron Construction
- 40KM of Primary & Secondary Conduit
- 513No. AGL Lights
- 50KM of Primary & Secondary Cable
Project Features
- 500m Extension to Runway 12/30
- New Parallel Taxiway K
- New Aprons RFDS & DPAW
- All new AGL